30. Commitments
    GROUP
June 2016
R000
  GROUP
June 2015
R000
 
30.1 Capital commitments    
  Approved and committed 84 245   135 442  
  Approved but not yet committed 174 077   145 493  
    258 322   280 935  
  Capital commitments approved and committed comprise the following:    
  Development costs 84 245   135 442  
  — Atterbury Value Mart 27 588   317  
  — Somerset Mall 25 242   36 627  
  — Woodlands Boulevard 11 164   7 530  
  — Canal Walk 9 855   7 288  
  — Clearwater Mall 4 942   37 270  
  — CapeGate 1 646   251  
  — Lakefield Office Park 1 037      
  — The Glen 915   1 716  
  — Willowbridge 706   101  
  — Somerset Value Mart 650   23  
  — Rosebank Mall 500   16 257  
  — Hyde Park Corner     28 062  
  The above capital expenditure will be financed out of available cash resources, banking facilities and debt capital market funding.        
           
30.2 Operating expense commitments        
  Hyprop has entered into various service contracts for the cleaning, upkeep and general maintenance of its investment property portfolio.        
  Operating expense commitments payable to service providers in future years have been classified as follows:        
  — Short-term contracts (up to one year) 3 093   1 534  
  — Medium-term contracts (greater than one year and up to five years) Nil   Nil  
         
  Contracts which can be terminated on one month’s notice have been included for one month only.      